Guides
Roof replacement
Re-roof or recover. Fast permit in many cities; product approval and fastening are the hold points.
Yes in almost every US city. Overlay vs. tear-off rules vary.
Related permits
Roofing · Building
Documents
- Product approval / NOA / Florida product approval where required
- Fastening schedule
- Existing roof photo set
- Contractor license
Steps
prepare · Owner or GC
Confirm which office issues the permit
Use the job address, not the mailing city. Inside city limits is usually the city building department. Outside is often the county. If two offices look possible, call both with the address and ask who issues the building permit for that property.
prepare · Owner or designer
Decide whether the work is permitted
Most structural, MEP, envelope, and change-of-use work needs a permit. Cosmetic finishes usually do not. When in doubt, ask the building department in writing and keep the answer with the job file.
prepare · GC / trades
Line up the people who can pull the permit
Many offices only issue to a licensed contractor, a registered designer, or a homeowner who signs an owner-builder affidavit. Check the state license before you apply.
apply · Applicant
Assemble the submittal
Application, site plan or survey, construction drawings, product approvals, energy forms, and owner / contractor affidavits. Incomplete packages are the most common reason a file sits.
apply · Applicant
File in the official portal
Create the account on the department website, pay the intake fee, and keep the record number. Do not start work. A complete application is not a permit.
review · Designer + applicant
Plan review and corrections
Building, zoning, fire, flood, and trade reviewers may each comment. Answer every comment in writing, mark the revised sheets, and resubmit the full corrected set the office asked for.
review · Applicant
Issuance and job-site posting
Pay remaining fees, print or download the approved set, and post the permit card where the inspector can see it. The stamped set is the only legal job copy.
build · Roofer
Call the dry-in / in-progress inspection
Many coastal AHJs want to see underlayment and fastening before the finished roof goes on. Do not finish over an uninspected deck.
closeout · GC
Final inspections
Trade finals usually precede the building final. Do not conceal failed work. Bring the approved set, prior tickets, and special-inspection reports.
closeout · Owner + GC
Close the file
Ask the department to final the permit. Collect the certificate of occupancy, certificate of completion, or finaled card. Keep as-builts, product approvals, and elevation certificates with the property.
Inspections
- Dry-in / in-progress — Deck exposed or underlayment in
- Roof final — System complete
Watchouts
- In HVHZ and many coastal zones, a roofing product that is 'code listed' elsewhere may still be rejected.
- More than two layers is often prohibited.